Waiward were the civil contractor for the Pembina Fox Creek Terminal Expansion Phase 2. The civil scope of work included rough grading of 5 acres, construction of access roadways, development of burrow pits and construction of a tank foundation including final grading of the containment area.
-
100,000 m3 of earthworks;
-
30,000 MT of gravel imported and placed;
-
12,000 m2 of containment floor preparation.